MINISTER OF STATE IN THE MINISTRY OF RAILWAYS(SHRI K. H. MUNIYAPPA)
(a) to (c) A statement is attached.
STATEMENT REFERRED TO IN REPLY TO PARTS (a) TO (c) OF UNSTARRED QUESTION NO. 1897 BY SHRI ARJUN MEGHWAL TO BE ANSWERED IN LOK SABHA ON 05-08-2010 REGARDING RAILWAY WORKSHOPS
(a) to (c) Yes, Madam. Modernisation of Railway workshops and Production units is a continuous process and is carried out in a need based manner. The details of such units recently taken up for modernisation are as under:
Workshop State Cost Year of Completion of
(Rs in approval the work
crores)
Kota Rajasthan 63.70 2007-08 The works are likely to
be completed in three years.
Hubli Karnataka 80.98 2007-08
Ponmalai Tamil Nadu 90.27 2007-08
Matunga Maharashtra 39.88 2007-08
Jhansi Uttar Pradesh 77.06 2007-08
Ajmer Rajasthan 72.75 2007-08
(Carriage)
Kanchrapara West Bengal 59.65 2009-10
Lucknow Uttar Pradesh 77.42 2009-10
Perambur Tamil Nadu 43.78 2009-10
(Carriage
& Wagon)
Rayanapadu Andhra Pradesh 61.71 2009-10
Kharagpur West Bengal 45.00 2007-08
Izatnagar Uttar Pradesh 68.13 2007-08
Lallaguda Andhra Pradesh 91.54 2007-08
Jamalpur Bihar 82.00 2008-09
Liluah West Bengal 87.00 2008-09
Ajmer(Loco) Rajasthan 58.73 2008-09
Perambur(Loco) Tamil Nadu 59.00 2008-09
|